Tram Track Renovation Works

Valid: Jun 15, 2026, 03:00Jul 12, 2026, 23:59
(modified at Jun 10, 2026, 09:33)

In order to maintain the uninterrupted operation of the tram lines, DKV Debreceni Közlekedési Zrt. will carry out track renovation works in several phases between June 15 and July 20, 2026.

TRAM TRACK RENOVATION WORKS

The company will perform rail replacement at three locations, totaling 228 track meters, before and after the Kossuth Square tram stop, as well as in front of number 23 Péterfia Street. At the Kossuth Square tram stop, the existing cracked asphalt track surface will be replaced with colored concrete pavement between the two rail replacement sections. On the Bem Square and Simonyi Street track sections, the company will carry out track regulation works over a length of 144 track meters at five locations.

PHASE I: WORKS OUTSIDE OPERATING HOURS (June 15 – June 20, 2026)

From June 15, 2026, until approximately June 20, during the first phase of the renovation, the track regulation works will take place after 6:00 PM and at night after the service closure, while maintaining tram traffic on Bem Square and Simonyi Street. The tram service will be uninterrupted again from the start of operations the next day, as no work will be carried out during the day.

Please note that the works may cause noise disturbances, so we ask for the patience of the residents in the affected area!

PHASE II: Works at Kossuth Square (June 22 – July 7, 2026)

The company has scheduled the works at Kossuth Square to coincide with the end of the school term and the start of the Campus Festival. During the construction period, from June 22 to July 7, 2026, trams 1 and 2 will not transport passengers between the Nagyállomás and Kálvin tér stops. Travel along the entire line will only be possible with transfers. The 1V-2V tram replacement buses departing from Nagyállomás will take passengers to Kálvin tér, where they can transfer to tram 1 heading towards the University and tram 2 heading towards Doberdó utca.

Route of the 1V-2V tram replacement buses:

Nagyállomás – Petőfi tér – Piac utca – Széchenyi utca – Tisza István utca – Hatvan utca – Bethlen utca – Hunyadi János utca – Rákóczi utca – Burgundia utca – Kossuth utca – Piac utca – Petőfi tér – Nagyállomás

 Stops of the 1V-2V tram replacement buses:

Nagyállomás (10 bus stop), Petőfi tér, Piac utca, Debreceni Törvényszék, Hatvan utca, Kölcsey Központ (Bethlen utca), Kölcsey Központ (Hunyadi János utca), Kálvin tér, Burgundia utca, Csokonai Színház, Kistemplom, Petőfi tér, Nagyállomás

PHASE III: Works at Kossuth Square and Péterfia Street (July 8-12, 2026)

The works will continue at Kossuth Square, and rail replacements will begin on the Péterfia Street section. During the works, tram traffic will be suspended along the entire line of tram 1, and 1V tram replacement buses will transport passengers instead. Tram 2 will continue to operate on the Kálvin tér – Doberdó utca – Kálvin tér line. The 1V tram replacement buses will provide connections between Nagyállomás and Kálvin tér for tram 2 services arriving and departing from Kálvin tér.

Route of the 1V tram replacement bus:

Nagyállomás – Petőfi tér – Piac utca – Kossuth utca – Burgundia utca – Rákóczi utca – Péterfia utca – Bem tér – Simonyi út – Pallagi út – Ady Endre út – Nagyerdei körút – Simonyi út – Bem tér – Péterfia utca – Rákóczi utca – Burgundia utca – Kossuth utca – Piac utca – Petőfi tér – Nagyállomás

Stops of the 1V tram replacement bus:

Nagyállomás (10 bus stop), Petőfi tér, Piac utca, Csokonai Színház, Burgundia utca, Rákóczi utca, Kálvin tér (temporary stop), Eötvös utca (temporary stop), Bem tér (temporary stop), Weszprémi utca (temporary stop), Nagyerdei körút (temporary stop), Aquaticum (Ady Endre út, temporary stop), Klinikai Központ Nagyerdei Campus (tram stop), Egyetem (tram stop), Medgyessy sétány (tram stop), Andaházi utca (temporary stop), Bem tér (temporary stop), Honvéd utca (temporary stop), Kálvin tér (bus stop), Burgundia utca, Csokonai Színház, Kistemplom, Petőfi tér, Nagyállomás.

Tickets can be used after transfers, but they must be validated on every vehicle.

ROAD TRAFFIC DURING THE WORKS

Participants in road traffic can expect speed restrictions and road narrowing alongside the tram line works on Péterfia utca, Bem tér, and Simonyi út. 

Affected routes